After a delay of over six years since its approval, the civil terminal on the upcoming Ludhiana worldwide airport (Halwara) is predicted to turn into operational in 2024, the official deadline of completion being March 31.
The much-touted worldwide airport undertaking, which CM Bhagwant Mann had mentioned will likely be named after Shaheed Kartar Singh Sarabha, would initially start with an interim terminal which is being constructed to deal with only one home flight (at one level of time) with a most of 300 passengers.

The Indian Air Pressure (IAF) station at Halwara is being upgraded into a world civil airport, a requirement of industrialists from Ludhiana since years. Whereas the terminal is 95% prepared, the IAF is but to finish the re-carpeting of the runway.
Amardeep Nehra, assistant common supervisor of Airport Authority of India (AAI), mentioned that the work is occurring at full tempo and the Public Works Division (PWD), the executing company of the Punjab authorities, has given a deadline of March 31, 2024 to finish work on the website.
“At current, we have now to make sure that the interim civil terminal is accomplished by March 31, 2024 so to begin home flights. The terminal constructing measures 2000 sqm and we have now constructed one new apron for touchdown of the airplane. Initially, the brand new infrastructure would deal with one home flight (AIRBUS A321) and 300 passengers (150 departure and arrival every). The present runway dimension is 3050 m x 45 m which is sufficient to deal with one flight. Will probably be expanded in future as per demand,” Nehra mentioned, including that work on the principle worldwide airport constructing will begin later.
Nehra mentioned that the undertaking will carry reduction to locals as they presently should journey to Delhi or Chandigarh to take flights. “There are visibility points on the presently current Sahnewal home airport on account of which Ludhiana-Delhi flight additionally fails to function repeatedly,” he mentioned, including that the interim terminal being constructed can be utilized for cargo and different functions later.
A go to to the location revealed that the brand new terminal constructing has only one conveyor belt (to deal with baggage). The contractor on the location mentioned that proper now they’re making ready the constructing for simply 150 passengers and will probably be expanded later.
Pardeep Kumar, government engineer (XEN), PWD, mentioned that of the almost Rs 53-crore undertaking value for terminal constructing and tarmac space building, the Punjab authorities has launched Rs 30 crore, which has been used. “There isn’t a downside of funds as of now. Work is occurring easily and being executed by Himachal Pradesh-based firm Synergy Thrislington,” he mentioned, including that originally your entire value will likely be incurred by the Punjab authorities, and later AAI will reimburse it.
Even because the Punjab cupboard permitted the undertaking in December 2018 underneath the earlier Congress authorities, and the Higher Ludhiana Space Growth Authority had taken possession of 161.27 acres solely in Could 2020. The civil work additionally began after inexplicable delays. The undertaking has missed a number of deadlines previously, together with one in June 2022 and one other in June 2023.